IN THE NW ENERGY
REQUEST TO ADD JUDITH GAP WINDPOWER
TO ITS GENERATION MIX
March
28, 2005, Billings, Montana
I am Russell Doty. I was
lead utility division counsel to the Montana Public Service Commission
for almost two years in the mid 1970s. I also was a contract administrative
law judge hearing some 60 cases over a five-year period for 13 different
public agencies in Minnesota. During that time I wrote several proposed
orders in utility rate cases ranging from 10 to 100 pages in length. I
speak here today as CEO/General Counsel of New World WindPower LLC, a company
I created in December 2004. It can be found on the web at newworldwindpower.com.
New World WindPower LLC will be marketing wind power in the Northwestern
Energy and other Montana, Wyoming and Colorado service areas. I testify
here without monetary compensation from any entity.
I
have good news for the Commission and for Montana consumers. This news
is summarized in four points.
SUMMARY: First,
questions about what capacity is needed to back additions of wind power
to a system and the costs resulting from adding wind have been addressed
in detail in a definitive accumulation of all major research in the area.
The authors of that compilation of research write:
The results to date
also lay to rest one of the major concerns often expressed about wind power:
that a wind plant would need to be backed up with an equal amount of dispatchable
generation. It is now clear that, even at moderate wind penetrations, the
need for additional generation to compensate for wind variations is substantially
less than one-for-one and is generally small relative to the size of the
wind plant. [1]
Second, the ancillary cost of providing power when the wind
does not blow is much smaller than has been represented by some and will
continue to decrease as we gain more experience with dispatching wind energy.
Those costs range from $0.00185 per kilowatt-hour of additional cost to
$0.0055/kilowatt hour depending on whether the amount of wind on the system
(penetration) is 3.5% or 29%. [2]
While there are load, internal generation capability, climate
and other differences between the utility systems in the accumulated research,
that experience creates at least a prima facie case for confidently
asserting that similar studies on Northwestern's system would produce similar
results. Extrapolating from these studies and adding these reported ancillary
costs to the base $31 per megawatt bid cost of power in the Northwest Energy
system would create a cost of wind power for Northwestern consumers in
the range of 3.247 cents to 3.327 cents per kilowatt hour of electricity
at the proposed 8% saturation.
Third, the capacity factor of windmills is not a measure of
how often the wind blows. To use it in that context introduces specious
arguments into the discussion of what using increasing amounts of wind
in a generation mix ultimately will cost Montana consumers.
Fourth, the
costs utilities have been charging to persons who have specifically ordered
electricity generated by the wind have come down significantly. For example,
the effective price of wind power charged to Xcel's Colorado customers
has been reduced from $0.025 cents per kilowatt-hour to $0.0076 cents per
kilowatt-hour. This has helped drive the cost of wind power down for other
utility customers.
CAPACITY NEEDED
TO BACK WIND: In addition to the compilation of studies on
the effect of wind on a generating system mentioned in the summary
above, I am including the most recent study I could find on the amount
of capacity needed to back up wind. [3] I ask the Commission to take administrative
notice of these studies and to find that they create a prima facie case
for the proposition that the proposed addition of wind power to NW
Energy system will be cost effective for Montana Consumers. This newest
study comes at the behest of the Minnesota Public Service Commission,
which directed the Minnesota Department of Commerce and Xcel energy
to update projections based on Xcel Energy's Northern Service Area,
which encompasses much of Minnesota, the Dakotas, Wisconsin and Michigan.
Xcel and its predecessor were one of the first utilities in the US
to have a significant amount of wind energy installed on its system.
In
November I visited the Buffalo Ridge area in southwestern Minnesota and
personally witnessed more than 500 utility scale windmills that span a
50+ mile area. The data for the study was taken from those windmills and
used to project the effect on Xcel's system of increasing the wind production
attached to it to 15% of the energy flowing over it coming from the wind.
Xcel has a peak system demand of about 9000 MW, projected to become 10,000. To
put it in perspective, that is more than 4 times the capacity of the entire
Colstrip complex. Xcel meets most of that peak load with internal generation
and buys about 800 MW on the open market.
Without
wind in the generation mix, in order to handle load variations, the Xcel system
needs 60 MW of excess capacity (over system peak load). The reason it does
not need more than that when its base load capacity is down for maintenance,
etc. is because it can obtain the needed power from the grid or other sources
it owns.
The
study found the addition of 1,500 MW of wind generation to the Xcel control
area increases the system regulation requirement by only 8 MW, from 60
to 68 MW to handle all of the variables that take place when the wind does
not blow and the wind speed fluctuates. The term "regulation requirement" is
a scientific reference to what has to be done to regulate the power on
Xcel's system from second to minute so that the quality of that power remains
in the 60-hertz range. So, on this short-term time scale, in the regulation
timeframe (the very fast fluctuations over the range of seconds and a few
minutes), wind variation looks very similar to the load variation that
Xcel is already handling with its 60MW regulation reserve. That reserve
only needs to be increased slightly when adding wind since adding the wind
only increases the combined regulation-scale fluctuation slightly. It is
emphasized that this is NOT dealing with the wind variation over the timescale
of hours (load following time frame) or days (unit commitment time frame)--just
the over the few minutes necessary to shift to any of the alternative fuels
on the large grid and regional transmission organization serving the utility
(regulation time frame). The costs of dealing with wind variation over
those load following and unit commitment time frames was also addressed
by the most recent Xcel study discussed below.
ANCILLARY
COSTS OF ADDING WIND POWER TO AN ELECTRIC SYSTEM: Nobody disputes the fact that wind speeds cannot be predicted
with high accuracy over daily periods, and the wind often fluctuates
from minute to minute and hour to hour. Consequently, electric utility
system planners and operators are concerned that variations in wind plant
output may increase the operating costs of the system. This concern arises
because the system must maintain balance between the aggregate demand
for electric power and the total power generated by all power plants
feeding the system. This is a highly sophisticated task that utility
operators and automatic controls perform routinely, based on well-known
operating characteristics for conventional power plants, sophisticated
decision-support algorithms and systems, and a great deal of experience
accumulated over many years. In general, the costs associated with maintaining
this balance are referred to as ancillary-services costs. [4]
There are typically three
time scales of interest in calculating total ancillary costs, which correspond
to the operation of the utility system and the structure of the competitive
electricity markets:
1) Unit-commitment horizon
of 1 day to 1 week with 1-hour time increments (Table 1, Col. E)
2) Load-following horizons
of 1 hour with 5- to 10-minute increments (intra-hour) and several hours
(inter-hour) (Table 1, Col. D)
3) Regulation horizon
of 1 minute to 1 hour with 1- to 5-second increments. (Table 1, Col. C)
Each
of these time frames has special planning and operating requirements and
costs.
The composite table of
ancillary service costs of major utilities studied to date is contained
in Table 1 below. [5] I have also added to that table from
the original study, a column converting the total per MWhr cost to total
per kilowatt-hour costs and adding the costs found in the most recent Xcel
study to the row at the bottom of the table.
TABLE
1
| |
|
$/MWh
|
|
| |
|
|
Time
Frame
|
|
|
| |
A
|
B
|
C
|
D
|
E
|
F
|
G
|
|
1
|
Study
|
Relative
Wind Penetration (%)
|
Regulation
|
Load
Following
|
Unit
Commitment
|
Total
in $/MWh
|
Total
in cents/KWh
|
|
2
|
UWIG/Xcel
|
3.50
|
0
|
0.41
|
1.44
|
1.85
|
0.00185
|
|
3
|
PacifiCorp
|
20.00
|
0
|
2.50
|
3.00
|
5.50
|
0.00550
|
|
4
|
BPA
|
7.00
|
0.19
|
0.28
|
1.00 - 1.80
|
1.47 - 2.27
|
0.00147 - 0.00227
|
|
5
|
Hirst
|
0.06
- 0.12
|
0.05
- 0.30
|
0.70
- 2.80
|
na
|
na
|
na
|
|
6
|
We Energies I
|
4.00
|
1.12
|
0.09
|
0.69
|
1.90
|
0.00190
|
|
7
|
We Energies II
|
29.00
|
1.02
|
0.15
|
1.75
|
2.92
|
0.00292
|
|
8
|
Great River I
|
4.30
|
|
|
|
3.19
|
0.00319
|
|
9
|
Great River II
|
16.60
|
|
|
|
4.53
|
0.00453
|
|
10
|
CA RPS Phase I
|
4.00
|
0.17
|
na
|
na
|
na
|
na
|
|
11
|
Xcel 2004 Study
|
15.00
|
0.23
|
|
4.37
|
4.60
|
0.00460
|
In a nutshell, the 2004
Xcel study noted Table 1, line 11) that even at the 15% of electricity
coming from the wind currently being called for by SB 415, which is pending
in the Montana House of Representatives, there is a very small regulation
time frame impact ($0.23/MWh), no significant cost impact in the load following
timeframe, and the largest impact ($4.37/MWh) in the unit commitment timeframe
(Col E). This clearly suggests that all the attention on the near-real-time
issues (imbalance penalties, etc.) is missing the real cost impacts and
we should usually be looking at the next day forecasting and scheduling
issue as the larger cost impact. And even then, the cost impact is not
all that large on most systems.
The authors of rows 1-10
of Table 1 offer several
other insights and generalizations about their data:
First, the incremental
cost of ancillary services attributable to wind power is low at low wind
penetration levels; as the wind penetration level increases, so does the
cost of ancillary services. Second, the cost of ancillary services is driven
by the uncertainty and variability in the wind plant output, with the greatest
uncertainty in the unit-commitment time frame, or day-ahead market. Improving
the accuracy of the wind forecast will result in lower cost of ancillary
services. Third, at high penetration levels the cost of required reserves
is significantly less when the combined variations in load and wind plant
output are considered, as opposed to considering the variations in wind
plant output alone. [6]
I used the Bonneville
Power Administration amounts found on line 4, Table 1 for the additional
costs that an addition of 8 % wind penetration would add to NW Energy's
costs because it appeared to be closest to the kind of system encountered
in Montana. However, even if the only higher ancillary cost found in the
4-8% wind penetration range were used (from line 8, Table 1), the cost
of wind power as proposed from the Judith Gap project would still not exceed
3.419 cents a kilowatt hour.
It should also be noted
that the authors of these studies have estimated the additional costs of
wind on the high side. For example, one will note from looking online at
the data from the original Xcel study found on line 2, Table 1 that the
0.00185 Total additional cost figure assume that the wind forecasting will
be wrong 50% of the time. Currently, wind forecasting is accurate 15-30%
of the time in the unit commitment time frame. If one assumes the 15-30%
accuracy figure in the cost calculation, it cuts the $1.44 $/MWh figure
for the unit commitment time frame on line 2 at least in half.
This reduced error rate
was apparently taken into account in the second Xcel study to obtain cost
data that reflected reality more closely. The study authors note, "For
the study year of 2010, the cost of integrating 1500 MW of wind generation
into the Xcel-NSP control area could be as high as $4.60/MWH of wind energy
where the hour by-hour forecast of wind for 16 to 40 hours ahead has a
mean absolute error of 15% or less."
Also,
there are other things that can be done to reduce costs to consumers of
increased use of wind power in the day-ahead time frame. For example, as
the 2004 Xcel study authors concluded, "The MISO [Midwest Independent System Operator)]
market cases demonstrate that the introduction of flexible market transactions
to assist with balancing wind generation in both the day-ahead scheduling
process and the day one hour ahead has a dramatic positive impact on the
integration costs at the hourly level. For example, in August the hourly
cost was reduced by two thirds."
Given the consistency
of these results, given the uncertainty in forecast natural gas and coal
gas costs, and given the fact that Xcel spent about $500,000 on its first
study, it is not necessary to incur that kind of cost here for additional
information that in all probability will not affect the range of costs
concerned appreciably. Wind power from Judith Gap will benefit NW Energy
consumer. Therefore, I respectfully request the Commission to find that
while extrapolation to Montana of the results of these studies is not perfect,
it is close enough for purposes of making a prudent and reasonable rate
finding allowing the Judith Gap wind energy project into the generation
portfolio of NW Energy at this time.
CAPACITY
FACTOR EXPLAINED: Recent reported statements about capacity factor demonstrate
that some state office holders misuse that concept. Capacity factor measures
what we would get from a windmill if it ran full-bore all of the time.
It is the amount of energy you get out of windmill divided by what is
theoretically possible given the rated design capacity of the windmill
if the wind blew all of the time.
People
misusing this concept usually say a windmill has a capacity factor of from
30-38%. It actually can be 42% in excellent wind. That does not mean as
Billings State Senator Jeff Essmann concluded in a recent letter to constituents,
that "the 62 to 70 percent of the time wind is not providing power" it
would have to be provided from more expensive natural gas.
The
capacity factor of windmills is not a measure of how often the wind blows. Most
wind farms produce some amount of electricity 65 to 80% of the time. They
just do not produce at the rate they would if the wind were blowing as
hard as it could all of the time.
For
example, the engineering studies on the General Electric wind farm at Lamar
in Southern Colorado indicate the farm produces electricity 88 to 90 percent
of the time (because windmills go around when the wind blows in the 4 to
8 mph range as well as when they twirl in higher wind speeds. Gearboxes,
tiltable blades and variable speed alternators and generators allow modern
windmills to take advantage of a variety of wind speeds.
To
better understand capacity factor let us consider an analogy to a hypothetical
small business owning four vehicles, a small car, a van and a small and
large truck. All of the vehicles are capable of traveling at speeds up
to 65-75 miles per hour. The larger vehicles cost more to operate and use
more gasoline. Nobody who drives any of the vehicles drives them at 65-75
miles an hour all of the time even though they have that capacity.
So
it is with energy generation sources. Nobody operates them at full capacity
all of the time. Coal power plants are shut down for various reasons during
the year usually routine maintenance. Nuclear power plants shut down to
refuel. Dams provide less electricity in the late summer and early winter
because water flows are low and so on.
All
the capacity factor means is that if the windmill were run at rated speed
in the 20-30 miles per hour range-like a car going 65-75 miles per hour-it
would produce 30 - 42 % of the electricity it is rated as being capable
of producing. You engineer the windmill to be able to take advantage of
the fact that the wind blows harder sometimes and softer sometimes. Likewise,
you engineer cars to be able to go 90 mph sometimes and 15 miles per hour
at other times.
So
when do you drive a small car or use wind power? When you can save money
or create less pollution by doing so. The same reason power dispatchers
dispatch energy from a dam, when there is water; from a windmill, when
there is wind and therefore no fuel or pollution control costs; or from
a coal-fired station in the unit commitment time frame, when the wind is
not forecasted to blow; or from a natural gas-fired facility only when
a lower cost fuel is not available.
Those
who say that natural gas power generation will have to be used when the
wind does not blow ignore the fact that natural gas is being used now. [7] A lot of the gas that is being used
can be replaced by wind power. They also ignore the fact that our unit
commitment time frame forecasting is good enough to allow base load coal
plants to replace the energy needed much of the time when the next day
is forecast to be calm. And they ignore the overwhelming data from the
Western Resource Advocates and other studies that projects that without
wind being 21% of the generation mix by 2020, our continued overuse of
natural gas will cost consumers in the 7 state Interior Rocky Mountain
West $5.3 billion a year too much each year in natural gas costs and $2
billion a year too much in electric costs. [8]
Regardless
of designed capacity, you use smaller vehicles when you don't need semi-trailers
to get around. You don't blow dust off your dining room table with a stick
of dynamite. And you don't continue to produce power with fossil fuel and
natural gas when cheaper, clean wind is available.
The
2004 Xcel study found:
While the penetration
of wind generation in this study is low [up to 15%] with respect to the
projected system peak load, there are many hours over the course of the
year where wind generation is actually serving 20 to 30% (or more) of the
system load. A combination of good plans, the right resource mix, and attractive
options for dealing with errors in wind generation forecasts are important
for substantially reducing cost impacts. [9]
RECENT COST REDUCTIONS FOR WINDPOWER:
The costs of wind power generally on a
system are coming down as the market grows, technology improves, and we
get more experience with what those costs actually are. Unlike natural
gas costs now hovering at a level more than double what they were four
years ago, those wind costs will continue to come down as we blend wind
power from the less expensive wind farms like that proposed for Judith
Gap with those from the older more expensive wind farms like those on the
Columbia River gorge. We can help drive those costs down by simply putting
more wind power online and creating a market for wind power.
This has happened in the systems of
utilities around the country, some 600 of which offer wind power to customers
who want it at a premium. Those premiums are not to be confused with the
ancillary costs discussed above. But even the premiums are being reduced.
For example, Windsource subscribers on the Xcel Energy Colorado system
currently pay $2.50 per 100 kWh block. However, Windsource purchases are
exempt from fuel costs and air quality rate riders, resulting in a current
net price of about $1.33 per block. That is, those who buy wind
do not have to pay for increased fuel costs or the costs of cleaning up
coal plants. The net premium is not based on the actual costs associated
with the program and the premium fluctuates with changes in the
fuel cost adjustment. Based on current rate riders/exemptions the new net
premium will be $0.76 per 100 kWh block. Xcel Energy is planning to change
the way Windsource charges appear on customer bills. Instead of the $2.50
Windsource line item and reversal of the fuel cost and air quality
charges, the bill would say something like: net
Windsource charge = $0.76 per 100 kWh block.
Prior to March of 2004, more than 30,000 Xcel Energy
customers and I paid for all of part of our energy from wind generation.
The results of this effort have helped to bring the cost of wind power
down dramatically. It would be tragic if Montana did not take advantage
of that cost reduction now, tragic and anti-consumer if we do not foster
the Judith Gap wind project.